In response to severe power shortages faced by a client in Najran, Energia undertook a monumental project to set up a 37 MW power rental plant. This involved deploying 50 generators of 1250 kVA each along with a range of Medium Voltage Transformers. Despite the complexity and time constraints, Energia successfully completed the installation, adhering to stringent safety standards.
PROJECT CAPACITY – 37MW
SYSTEM VOLATEG – 13.8KV
Mode of Operation: Base Load
Duration: June 2019 to November 2021
Challenges:
- The project presented significant challenges due to the tight timeframe imposed by the client for
installation and commissioning. - Energia rose to the occasion, overcoming hurdles with the unwavering support of management and the dedicated site team.
- All equipment, including fuel tanks and accessories, were supplied and installed with meticulous attention to safety protocols.
Journey:
- Operational readiness was paramount, as evidenced by the swift response to start the plant upon request from the client’s Control Room in Abha.
- A standby contingency plan was in place with 2 to 3 spare machines, ensuring uninterrupted power supply in case of emergencies.
- Despite initial staffing constraints, Energia transformed challenges into opportunities by providing rigorous training to the team, fostering a culture of collaboration and dedication.
- The team’s hard work and commitment were duly recognized and rewarded by management, further motivating them to excel.
Rewards:
- Seamless coordination with the client, coupled with strict adherence to Health, Safety, and Environmental standards, enhanced operational efficiency.
- The project served as a learning curve for Energia, contributing to professional growth and laying a solid foundation for future endeavors.
Key Points Highlighted:
- Urgent Response: Energia’s prompt action to address the client’s power shortage crisis underscores its reliability and efficiency.
- Complexity and Challenges: The project’s complexity and tight timeframe were acknowledged, highlighting Energia’s ability to navigate adversities.
- Team Effort: The success of the project was attributed to the collective efforts of Energia’s skilled workforce, emphasizing the importance of teamwork & training.
- Client Satisfaction: Energia’s commitment to meeting the client’s requirements and ensuring operational excellence strengthened its rapport with the client.
- Learning and Growth: The project served as a valuable learning experience, contributing to professional development and paving the way for future successes.