In response to severe power shortages faced by a client in Hail South Area when no other Power Rental provider registered with SEC was willing to provide power due to severe limitation of time in commissioning the same. We at Energia undertook the challenging project to set up a 33 MW, 34.5KV, power rental plant and commissioned the same in 35 days time at 3 different locations. This involved deploying 58 generators of 1250 kVA each along with a range of Medium Voltage Transformers. Despite the complexity and time constraints, Energia successfully completed the installation, adhering to stringent safety standards.
PROJECT CAPACITY – 33 MW
SYSTEM VOLTAGE – 34.5 KV
Mode of Operation: Island Load
Duration: June 2021 to 31st August 2022
Challenges:
- The project presented significant challenges due to the tight timeframe imposed by the client for installation and commissioning at three different locations.
- Energia rose to the occasion, overcoming hurdles with the unwavering support of management and the dedicated site team.
- All equipment, including fuel tanks and accessories, were supplied and installedwith meticulous attention to safety protocols at Locations namely; Hait, Hulayfah and Kahafah.
Journey:
- Swift response to start the plant upon request from the client’s control room in Hail showcases operational readiness.
- A standby contingency plan was in place with 2 to 3 spare machines, ensuring uninterrupted power supply in case of emergencies.
- Consequently, the site contains a lot of stones underneath the soil and earthing resistance was also very high, hence we did special earthing and reduced the earthing resistance to below 1 ohm.
- The team’s hard work and commitment were duly recognized and rewarded by management, further motivating them to excel.
Rewards:
- Seamless coordination with the client, coupled with strict adherence to Health, Safety, and Environmental standards, enhanced operational efficiency.
- The project served as a learning curve for Energia, contributing to professional growth and laying a solid foundation for future endeavors.
Key Points Highlighted:
- Urgent Response: Energia’s prompt action to address the client’s power shortage crisis underscores its reliability and efficiency.
- Complexity and Challenges: The project’s complexity and tight timeframe were acknowledged, highlighting Energia’s ability to navigate adversities.
- Team Effort: The success of the project was attributed to the collective efforts of Energia’s skilled workforce, emphasizing the importance of teamwork and training.
- Client Satisfaction: Energia’s commitment to meeting the client’s requirements and ensuring operational excellence strengthened its rapport with the client.
- Learning and Growth: The project served as a valuable learning experience, contributing to professional development and paving the way for future successes.